Project Name:
Karaganda - Astana Road Rehabilitation Project

Name Of Client:
Ministry of Transport and Communications

Detail Narrative Description of Project:
Existing Karaganda to Astana Road is 220km long republican road funded by the Islamic Development Bank. It is integral part of the major trunk road connecting new capital Astana in the north to its commercial center Almaty south-east of the country.

Project Location within Country: Akmola Oblast (KZ)

Professional Staff Provided by the company: 15

No.of Man-Months: 18,5

Start Date: 5/4/2002

Completion Date(month/year): 3/10/2002

Services: The scope of the project was to prepare the detailed engineering design for 54km long Vishnevka - Astana section of the road for execution by the contractor, Eksen KZ. This included: - topographic surveys; - geometric design for new realignment section of the road; - new full-depth and overlay pavement designs; - structural design including bridges/culverts rehabilitation, new design for railway overpass; - road drainage design; - road furniture and junctions design; - quantity estimates.

Name of Associated firm(s):
ESKSEN KZ (JV Turkey-Kazakhstan)

No of Man-Month Of Professional Staff
Provided by associated firm(s):
0

Name of Senior Staff: Omarkhan Birimzhan, Project Director - overall project coordination; Rustam Ishenaliev, Team Leader - daily supervision and management of project activities

 